Public
Health Engineering Department
Digha has turned out to be one of the favourite destinations where a causal day tripper wishes to visit repetitively in a bid to “drink life to the lees” for some time while shoving out the mundane activities that fatigues the human intellect to the nadir of restiveness.
A flashback of not so remote period will entail the fact
behind the wobbly and asymmetrical scenario of the incumbent sanitary sewage
scheme at Digha. The Sanitary Sewerage
Scheme for Digha was sanctioned earlier in the year 1996 for an estimated cost
of Rs. 4.09 crores considering a design population of 17,000 in the design year
2011. After laying of about 1825 mtr. sewer line some problems of sand boiling
were faced in some places and work was suspended, temporarily, in the year
1997. To overcome such problem re-design of the entire system was done in 1999
to safeguard against sand boiling problem and suspended work resumed in the
year 2000. Based on the re-design a considerable part of the work was completed
within the sanctioned amount of Rs. 4.09 crores. However as the entire sewer
network had been re-designed it was not possible to execute all works of the
scheme within the sanctioned amount due to cost escalation and other allied
corollaries. Accordingly, revised estimate was prepared subsequently and it was
proposed to execute the work in 2 phases. Value of the revised estimate was Rs.
12.51 crores comprising of works for Phase-I and Phase-II. Estimated amount for
Phase-I works was proposed as Rs. 8.89 crores and for Phase-II works was Rs.
3.62 crores. But the said revised estimate was not sanctioned and as a
consequence, works remains suspended till now for want of requisite fund.
Objective of the Proposed Sewerage
System
With the growing population the management of solid waste turned out to be a critical affair as if untreated wastewater is allowed to accumulate, the decomposition of the organic matter it contains can lead to the production of large quantities of mal-odorous gases. In addition the untreated wastewater usually contains numerous pathogenic or disease-causing microorganisms that dwell in the human intestinal tract. It also contains nutrients, which can stimulate the growth of aquatic plants, and it may contain toxic compounds. For these reasons, the immediate and nuisance-free removal of wastewater from its sources of generation, followed by treatment and disposal, is not only desirable but also necessary for the society to improve the hygienic condition as well as to maintain the environmental standard of the area. The ultimate goal - wastewater management - is the protection of the environment in a manner commensurate with economic, social, and political concerns.
The objective of the sewage treatment is to stabilize
decomposable organic matter present in the sewage so as to produce an effluent
and sludge which can be disposed of in the environment without causing health
hazards or nuisance. Health hazards are also created due to the bacteriological
contamination in the underground water and also to the surface water bodies.
Therefore, treatment of Sanitary Sewage in the Digha area becomes essential to
safeguard the health hazards of the people of the area as well as to the
visiting tourists and also for the protection of the coastal ecosystem of the
popular beach resort.
Proposed Project Component:
In the renovation work of the present scheme, different diameter sewer lines are to be laid except sewer lines constructed earlier. In the proposed system, the sewer network of 18,646 meter length of different diameters will collect sewage from the entire command area and will transmit the same to the Sewage Treatment Plant. Out of total sewer line, a length of 6,496 meter of different diameter sewer lines were laid earlier according to the initial sanction and remaining 12,150 meter sewer lines of different diameter are to be laid as per proposed renovation work. Sewer lines already constructed earlier are to be cleaned thoroughly to make those lines functional as those lines are lying idle for quite a long time.
The sewerage network of the proposed renovation scheme has been designed in such a way so that these Sewage Pumping Stations can function independently. Accumulated sewage of these pumping stations will be pumped separately and will be collected in a collection chamber before entering into the sewage treatment plant and will then be distributed uniformly from the collection chamber to the treatment ponds.
The treatment process to be adopted for the present scheme has been decided after comparative study of advantages and disadvantages among several treatment technologies available now-a-days and after such comparative study it has been decided that waste stabilization pond comprising of anaerobic, facultative and maturation pond will be the best option for treating sewage of Digha Township. The degree of treatment to be provided has been decided by comparing the raw waste water characteristics with respect to the required standard of final effluent to be discharged according to the set provisions. Main advantage of this process is that this process does not require any mechanical equipment for operation and as a result no electrical energy will be required for the plant operation which in the process will drastically cut down the operational cost. But the main disadvantage of the process is that it requires large area of land but as the land is available free of cost from Digha Sankarpur Development Authority (DSDA) waste stabilization pond has been selected for the treatment of sewage of Digha Township. Waste stabilization pond is also the simplest of all waste treatment technologies available for sewer waste water because of its simplicity and reliability of operation. A stabilization pond is simply a shallow body of water contained in an earthen basin exposed to sun and air.
The total estimated cost of the renovation work of Digha Sanitary Sewerage Scheme comes to `35.59 crores comprising of costs related to civil works as well as mechanical/electrical works. This cost also includes charges for service connection as well as cost of trial run coupled with operation and maintenance costs for the initial 3 years after commissioning of the project.
Execution of the present scheme will be done through turnkey contracts with provision of 3 years operation and maintenance by the executing agency including performance guarantee after successful commissioning of the entire system. Thereafter, the scheme will be handed over to the Digha Sankarpur Development Authority (DSDA) for operation and maintenance.
Along with the aforementioned sewage network PHED is supposed to construct a building within in the adjacent areas of Hospital at Digha. The proposed building will serve multiple purposes as it will have allotted room spaces for discharging administrative duties and responsibilities, laboratory, staff quarters, rest shed, stores, etc. An internal pathway along with street lighting and fences embedded with bushes and shrubberies surrounding the building will be put together. As ICZM Project is an environmental project the proposed building will be based on LEED green building rating system. The target is to achieve Platinum certification provided by LEED rating system. A building with Platinum certification means it has taken care of the sustainability issues by recognizing the performance in five key areas of human and environmental health:
·
sustainable
site development
·
water
efficiency
·
energy
efficiency
·
materials
selection
·
indoor
environmental quality
Operation
& Maintenance Planning
Operation and maintenance cost of
the scheme after initial 3 years has been assessed as `1.80 crores including cost of manpower and electricity
charges which will guide the DSDA to decide upon the policy of operation and
maintenance. Based on the policy of operation and maintenance DSDA has to
finalize appropriate tariff structure to be recovered from the consumers. For
the purpose of recovery of operation and maintenance cost from consumers DSDA
also has to finalize suitable cost recovery mechanism. In addition, DSDA has to
create a separate cell for the operation and maintenance of the entire system.
Maintenance work generally consist of good
"house-keeping" which mainly entails regular weed and grass trimming
and other usual measures to prevent mosquito breeding. Floating scums and mats
will also have to be removed. Regular visits by an operator will be there to
ensure that the waste stabilization ponds are operating satisfactorily. When
the characteristic green colour of a pond changes to grey, brown or pink, it is
generally a sign of overloading and anaerobic conditions, often accompanied
with mal-odours. When this occurs as a result of temporary overload, the
wastewater will have to be by-passed for some time to allow the pond to restore
itself. Repeated occurrences can be corrected by taking more permanent measures
such as enlarging the existing ponds to cater to increased load. Occasionally,
embankments may need dressing once every few years. Desludging of ponds will
also be necessary at suitable intervals as per requirement.
In this regard, regular and periodic samplings at different points are to be done for a clear assessment of the performance of the entire system. Installation of a simple measuring weir in the inlet chamber will be there to assess whether flow conditions have changed or BOD or other characteristic of the wastewater or both have changed.
No comments:
Post a Comment